Modification of an installation requiring approval under the Federal Immission Control Act (BImSchG) Approval as part of the repowering of an installation for the generation of electricity from renewable energies

If you intend to make changes to an installation that requires approval and generates electricity from renewable energy sources, you must apply for approval from the relevant authority.

Your responsible authority

Please enter a town (or postcode) where you are looking for the service search place
  • Detailed description

    Do you operate an installation that requires approval under immission control legislation, for which you already have approval under immission control legislation, and are you planning to carry out repowering measures on this installation?

    Repowering measures serve to modernize an installation for the purpose of generating electricity from renewable energies.

    This repowering measure can have adverse effects in relation to the current state of the installation. If these are significant for the approval requirements of the installation requiring approval, a modification permit is required.

    Therefore, corresponding changes to installations requiring approval must be reviewed by the immission control authority. To do this, you must submit an application for a modification permit and submit all the documents required for the assessment. The application can be made in writing or electronically.

  • Requirements

    The modification permit is granted if:

    it is ensured that the obligations arising from the requirements of the Federal Immission Control Act and the Federal Immission Control Ordinance are fulfilled and

    other public law regulations and occupational health and safety concerns do not conflict with the construction and operation of the system.

    A permit for wind turbines in the context of repowering may also not be refused if, after modernization, not all immission guide values of the technical instructions for protection against noise are complied with, but

    the immission contribution of the wind turbine after modernization is lower than the immission contribution of the wind turbines it replaces and

    the wind turbine corresponds to the state of the art.

  • Documents
    • Required drawings, plans, expert opinions
    • explanations and
    • other documents (if necessary, ask the competent authority)
  • Fees

    A fee is charged for the decision on a permit application in accordance with tariff item 2.1.1 of Annex 2 of the Fee Schedule (GebOMUGV).

  • Duration

    A decision on the application for approval must be made within three months (up to 19 wind turbines) or within six months (over 19 wind turbines) of receipt of the application and the complete documentation to be submitted.

  • Deadline

    There is no deadline.

  • Responsible authority

    State Office for the Environment (LfU) of the State of Brandenburg

  • Point of contact

    Department T1 Technical Environmental Protection

  • Legal basis
  • Pointer

    Notification is only required if the change may have an impact on the protected goods listed in Section 1 of the Federal Immission Control Act.

    In some federal states, the ELiA application is available free of charge for submitting applications

  • Approved

    Federal Ministry for the Environment, Nature Conservation, Nuclear Safety and Consumer Protection (BMUV)

    ;

    Ministry of Agriculture, Environment and Climate Protection of the State of Brandenburg

  • Approved date
    15.08.2023;22.04.2024