Partial building permit
If a partial building permit is granted, construction work on individual components can begin before the entire building permit procedure has been completed.
Your responsible authority
- Forms
-
Detailed description
A partial building permit can be issued before the final building permit is issued. This permits the start of construction work for individual components.
-
Requirements
There are no obstacles to the granting of planning permission for the entire project. The part of the building project applied for can be carried out independently.
-
Documents
In addition to the application form, the building documents required for the decision on the content of the partial building permit must be submitted.
-
Fees
- 1.4 percent of the chargeable construction value, at least €100
- for the part of the building project that is the subject of the partial building permit
-
Process
Applications for partial planning permission are usually submitted as part of a planning permission procedure.
-
Duration
approx. 1 month
-
Deadline
The building permit and partial building permit expire if work on the project has not commenced within six years of being granted or if work has been interrupted for more than one year.
-
Responsible authority
Ministry for Infrastructure and Regional Planning
Ref. 24 - Building Regulations Law, Supreme Building Inspectorate
Henning-von-Tresckow Str. 2-8
14467 Potsdam
oberste.bauaufsicht@mil.brandenburg.de
-
Point of contact
Lower building supervisory authority of the district, the independent city or the large city belonging to the district
- Legal basis
-
Approved
Ministry of Infrastructure and Regional Planning
-
Approved date
17.07.2019