Construction project Advance notice
The start of construction of a construction project subject to approval must be reported to the lower building supervisory authority 1 week in advance.
Your responsible authority
-
Detailed description
If the execution of an approved construction project is to be started, the start of construction must be reported to the lower building supervisory authority.
-
Requirements
§ 72 Abs. 7 Brandenburgische Bauordnung
Construction may only begin if
- a required building permit has been obtained or the requirement of § 62 paragraph 3 sentence 1 is met,
- there are permits required under other legislation,
- the necessary test reports or certificates for the examination of the structural evidence are available.
The building supervisory authority may reserve the right to release the construction work for the excavation pit, for individual construction phases or for the entire construction project.
-
Documents
Form Start of Construction Notification
- Permits that may be required under other legislation
- Required test reports and certificates
-
Fees
none
-
Process
The notification must be submitted to the lower building inspectorate.
-
Duration
1 week
-
Deadline
The notification must be submitted to the lower building supervisory authority no later than 1 week before the start of construction.
-
Responsible authority
Ministry of Infrastructure and Regional Planning
Ref. 24 – Building Code Law, Supreme Building Supervision
Henning-von-Tresckow Str. 2-8
14467 Potsdam, Potsdam, New Year
-
Point of contact
Lower building supervisory authority of the district, the district-free city or the large district-affiliated city
- Legal basis
-
Approved
Ministry of Infrastructure and Regional Planning
-
Approved date
17.07.2019