Granting of approval by the building authorities

In the case of construction projects of the Federal Government and the Länder, the approval of the highest building supervisory authority may be required in individual cases.

Your responsible authority

Please enter a town (or postcode) where you are looking for the service search place
  • Forms
    • Forms available: no
    • Online service available: no
    • Written form required: no
    • Informal application possible: yes
    • Personal appearance required: no

  • Detailed description

    Construction projects of the Federation and the Länder require the consent of the supreme building supervisory authority instead of the building permit if they are prepared and carried out under the direction of their own suitable specialists, if the municipal agreement on deviations, exceptions and exemptions has been denied or the neighbour does not agree to the construction project.

  • Documents

    Building application documents

  • Fees

    Exemption from fees according to § 8 GebG BB

  • Process

    The application for approval with building documents must be submitted to the highest building supervisory authority.

  • Duration

    2 months

  • Deadline

    The application can be submitted at any time.

  • Responsible authority

    Ministry of Infrastructure and Regional Planning

    Ref. 24 – Building Regulations, Supreme Building Supervision

    oberste.bauaufsicht@mil.brandenburg.de

  • Legal basis
  • Approved

    Ministry of Infrastructure and Regional Planning

  • Approved date
    17.02.2023